Truck Planning and Daily Work Targets in Highway Construction

Main Article Content

Rajdeep Singh Grewal
Dapinder Deep Singh
Aman Sirohi
Pavitar Singh
Gurpreet Singh

Abstract

Road construction needs a steady supply of materials from the mixing plant to the site. This study examined how the daily work length and number of trucks related to material deliveries for granular sub-base and wet mix macadam. Records from 62 highway projects included 60 observations for each of these two road layers. An Arena computer model followed the movement of materials and equipment. A Taguchi design compared working conditions, and 16 further cases examined work length, truck numbers and travel delay. Work length showed the largest change in the signal-to-noise score, at 5.60 dB. The full material requirement for 0.3 km was delivered at every tested delay. For 0.6 km, the delivered amount ranged from 85% to 100% of the requirement. For a uniform road section, 85% was enough to supply 0.510 km. The findings connect the daily target with the amount reaching the site. Truck numbers should be chosen together with work length and the capacity for loading, mixing and site work.

Article Details

How to Cite
Singh Grewal, R., Deep Singh, D., Sirohi, A., Singh, P., & Singh, G. (2026). Truck Planning and Daily Work Targets in Highway Construction. CINEFORUM, 66(S5), 665–672. https://doi.org/10.66669/cineforum.v66iS5.1993
Section
Original Articles

References

Abdelmegid, M. A., González, V. A., Poshdar, M., O’Sullivan, M., Walker, C. G., & Ying, F. (2020). Barriers to adopting simulation modelling in construction industry. Automation in Construction, 111, 103046. https://doi.org/10.1016/j.autcon.2019.103046

AbouRizk, S. M., & Halpin, D. W. (1990). Probabilistic simulation studies for repetitive construction processes. Journal of Construction Engineering and Management, 116(4), 575–594. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:4(575)

Alvanchi, A., Baniassadi, F., Shahsavari, M., & Kashani, H. (2021). Improving materials logistics plan in road construction projects using discrete event simulation. Engineering, Construction and Architectural Management, 28(10), 3144–3163. https://doi.org/10.1108/ECAM-08-2018-0317

Chen, Z., & Hammad, A. W. A. (2023). Mathematical modelling and simulation in construction supply chain management. Automation in Construction, 156, 105147. https://doi.org/10.1016/j.autcon.2023.105147

Cheng, J. C. P., Law, K. H., Bjornsson, H., Jones, A., & Sriram, R. (2010). A service oriented framework for construction supply chain integration. Automation in Construction, 19(2), 245–260. https://doi.org/10.1016/j.autcon.2009.10.003

Choudhari, S., & Tindwani, A. (2017). Logistics optimisation in road construction project. Construction Innovation, 17(2), 158–179. https://doi.org/10.1108/CI-03-2016-0014

de Lima, R. X., Nobre Júnior, E. F., Prata, B. de A., & Weissmann, J. (2013). Distribution of materials in road earthmoving and paving: Mathematical programming approach. Journal of Construction Engineering and Management, 139(8), 1046–1054. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000666

Fente, J., Schexnayder, C., & Knutson, K. (2000). Defining a probability distribution function for construction simulation. Journal of Construction Engineering and Management, 126(3), 234–241. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:3(234)

González, V., & Echaveguren, T. (2012). Exploring the environmental modeling of road construction operations using discrete-event simulation. Automation in Construction, 24, 100–110. https://doi.org/10.1016/j.autcon.2012.02.011

Halpin, D. W. (1977). CYCLONE—Method for modeling job site processes. Journal of the Construction Division, 103(3), 489–499. https://doi.org/10.1061/JCCEAZ.0000712

Jabri, A., & Zayed, T. (2017). Agent-based modeling and simulation of earthmoving operations. Automation in Construction, 81, 210–223. https://doi.org/10.1016/j.autcon.2017.06.017

Jaśkowski, P., Sobotka, A., & Czarnigowska, A. (2018). Decision model for planning material supply channels in construction. Automation in Construction, 90, 235–242. https://doi.org/10.1016/j.autcon.2018.02.026

Joshaghani, A., Ramezanianpour, A. A., Ataei, O., & Golroo, A. (2015). Optimizing pervious concrete pavement mixture design by using the Taguchi method. Construction and Building Materials, 101, 317–325. https://doi.org/10.1016/j.conbuildmat.2015.10.094

Lee, C., Cha, M., Kim, H., & Cho, H. (2023). Detailed activity-based earthwork scheduling model to aid during the planning stage of road construction. Applied Sciences, 13(23), 12902. https://doi.org/10.3390/app132312902

Lee, H., & Kim, S. (2025). Optimum equipment allocation under discrete event simulation for an efficient quarry mining process. Processes, 13(7), 2215. https://doi.org/10.3390/pr13072215

Martinez, J. C. (2001). EZStrobe—General-purpose simulation system based on activity cycle diagrams. Proceedings of the 2001 Winter Simulation Conference, 2, 1556–1564. IEEE. https://doi.org/10.1109/WSC.2001.977485

Montenegro Defaz, M. F., & Awuah-Offei, K. (2026). Utilizing digital twins to model and optimize hydraulic excavator operator performance through Arena simulation. Mining, Metallurgy & Exploration, 43, 3131–3147. https://doi.org/10.1007/s42461-026-01598-w

Press Information Bureau. (2026, August 12). India’s infrastructure transformation: From connectivity to capacity. Government of India. https://www.pib.gov.in/PressReleasePage.aspx?PRID=2298526

Rashid, K. M., & Louis, J. (2022). Integrating process mining with discrete-event simulation for dynamic productivity estimation in heavy civil construction operations. Algorithms, 15(5), 173. https://doi.org/10.3390/a15050173

Sargent, R. G. (2013). Verification and validation of simulation models. Journal of Simulation, 7(1), 12–24. https://doi.org/10.1057/jos.2012.20

Vrijhoef, R., & Koskela, L. (2000). The four roles of supply chain management in construction. European Journal of Purchasing & Supply Management, 6(3–4), 169–178. https://doi.org/10.1016/S0969-7012(00)00013-7

Zamani, V., Taghaddos, H., & Gholipour, Y. (2023). Sensor-fused simulation-based decision support system for earthmoving projects. Automation in Construction, 156, 105117. https://doi.org/10.1016/j.autcon.2023.105117

Zamani, V., Yavari, E., & Taghaddos, H. (2024). A science mapping lens on discrete event simulation applications in construction engineering and management. Automation in Construction, 166, 105625. https://doi.org/10.1016/j.autcon.2024.105625

Zeng, N., Ye, X., Liu, Y., & König, M. (2024). BIM-enabled Kanban system in construction logistics for real-time demand reporting and pull replenishment. Engineering, Construction and Architectural Management, 31(8), 3069–3096. https://doi.org/10.1108/ECAM-01-2022-0036