Retrospective Analysis of Tunnel Squeezing – A Case Study of Tunnel No. 10 along Sivok – Rangpo Railway Project (SRRP), Darjeeling, West Bengal, India.

Main Article Content

Saradindu Mukherjee
Sanket Tirpude
Somnath Mishra

Abstract

The Government of India has undertaken the construction of “Sivok – Rangpo Railway Project (SRRP)” to establish rail route connectivity between Sivok (in West Bengal) and Rangpo (in Sikkim). The railway line consists of total 14 tunnels of variable lengths with connecting bridges. The Tunnel No. 10, being the longest tunnel with 5300 m length, underpasses maximum height of overburden i.e. approximately 800m. As an integral part of the geologically complex Himalayan Orogenic Belt, the tunnelling ground poses various threats towards safe and economic construction of the Tunnel. During construction phase, the tunnel has experienced squeezing and rock burst that basically represent high in-situ stress induced tunnel instability. Below about 725m overburden, the tunnel suffered from very severe to extreme tunnel squeezing and had to undergo re-excavation. To figure out the root cause of tunnel squeezing, an attempt to estimate the ratio of average horizontal stress to vertical stress (Earth Pressure Co-efficient or ‘k’) has been made from measured tunnel strain data. Considering the vertical rock pressure as minimum principal stress direction, complete in-situ stress tensor has been estimated. Retrospective analysis for tunnelling ground behavior has been exercised based on laboratory tested rock strength parameters and 50% reduced rock strength parameters (due to time dependent deformation or creep deformation) under the influence of ‘Back-analyzed’ in-situ rock stress magnitudes. Empirical, Semi-Empirical, Analytical (Convergence Confinement Method) as well as Numerical (Finite Element Method) analyses confirm the apprehension of very severe to extreme tunnel deformation that appears with concordance to the reality..

Article Details

How to Cite
Mukherjee, S., Tirpude, S., & Mishra, S. (2026). Retrospective Analysis of Tunnel Squeezing – A Case Study of Tunnel No. 10 along Sivok – Rangpo Railway Project (SRRP), Darjeeling, West Bengal, India. CINEFORUM, 66(S5), 324–339. https://doi.org/10.66669/cineforum.v66iS5.1437
Section
Original Articles

References

G. L. Shrestha, Ph.D. thesis “Stress induced problems in Himalayan tunnels with special reference to squeezing”, 2006

E. Hoek, and P. Marinos, “Predicting tunnel squeezing problems in weak heterogeneous rock masses.” Tunnels Tunnel Int; 32 (11 and 12) p. 45–51 and p. 34–36, 2000

E. T. Brown, and E. Hoek, “Trends in relationships between measured in-situ stresses and depth.” In International Journal of Rock Mechanics and Mining Sciences & Geomechanics Abstracts (Vol. 15, No. 4, pp. 211-215). Pergamon, 1978

Md. Hadi Alam, and M. K. Sharma, “Criticalities encountered in Construction of (HRT) Head Race Tunnel of Kameng Hydro Electric Project (600MW), In Arunachal Pradesh, India.” International Journal of Scientific & Engineering Research, Volume 5, Issue 9, ISSN 2229-5518, September 2014

R. K. Goel, J. L. Jethwa, and A. G. Paithankar, “Indian experiences with Q and RMR systems.” Tunnelling and Underground Space Technology Incorporating Trenchless, 10 (1), 97–109, 1995

C. Carranza-Torres, and C. Fairhurst, “Application of the convergence confinement method of tunnel design to rock masses that satisfy the Hoek-Brown failure criteria.” Tunnelling and underground space Technology,15(2), Pages 187-213, 2000

N. Vlachopoulos, and M. S. Diederichs, "Improved longitudinal displacement profiles for convergence confinement analysis of deep tunnels." Rock mechanics and rock engineering 42.2: 131-146, 2009

B. Singh, and R. K. Goel, "Rock Mass Classification - A Practical Approach in Civil Engineering”, 1999

J. A. Hudson, F. H. Cornet, and R. Christiansson, “ISRM Suggested Methods for rock stress estimation—Part 1: Strategy for rock stress estimation,” Rock Mech. Rock Eng. 2003

E. M. Anderson, “The dynamics of faulting and dike formation with application to Britain.” Oliver and Boyd, 2nd Edition, Edinburgh, 133147, 1951

H. Fossen, “Structural geology”, Cambridge, U.K., Cambridge University Press, 2016

“Geotechnical Interpretative Report for Tunnel T9 & T10.”

“Geotechnical Interpretative Report for Tunnel T3 & T4.”

Instrumentation & Monitoring Reports for Tunnel T9 & T10, for the months from November 2023 to December 2024.

RESS (before re-excavation) issued by IRCON.

DEFORMATION REPORT prepared by Client, Designer and Contractor before re-excavation of Tunnel No 10 (SRRP).

https://www.world-stress-map.org.